The Financial Impact of Schedule Delays on The Kucing Liar (KL) Project at PT Freeport Indonesia: A Scenario-Based Discounted Cash Flow Analysis
DOI:
https://doi.org/10.46799/adv.v4i10.724Keywords:
Discounted Cash Flow, Schedule Delay, Scenario Analysis, Sensitivity Analysis, Real Terms, Block Cave MiningAbstract
PT Freeport Indonesia (PTFI) is transitioning from the depleted Grasberg open-pit mine to underground block-caving operations, with Kucing Liar (KL) representing its largest underground mining project. Production is scheduled to commence on July 1, 2029, while the current mining license expires in 2041. Given this fixed expiration date, schedule delays could defer revenue generation and reduce project value, highlighting the need for a quantitative assessment of delay-related financial losses and schedule-protection investments. This study developed a deterministic discounted cash flow (DCF) model using the 3Q26R2 mine plan, the 2023 feasibility study, and company cost data covering 2021–2041, expressed in constant 2026 U.S. dollars. The analysis incorporated three scheduling scenarios, six cost-escalation variants, and sensitivity assessments. The base-case net present value (NPV) was $9,408 million at a 10% real discount rate, with a projected payback period ending in 2032. A six-month delay reduced NPV by $665 million, while a 12-month delay combined with a 10% cost escalation resulted in a $1,569 million reduction (16.7%). The estimated financial impact averaged $111 million per month of delay, increasing to $138 million when capital expenditures could not be rescheduled. Approximately two-thirds of the NPV reduction resulted from deferred cash flows, while the remaining loss was attributable to production extending beyond the 2041 license expiration. Across cost-escalation scenarios, the financial impact ranged from $110 million to $119 million per month, with schedule performance demonstrating approximately three times greater influence on project value than development capital expenditures. The findings established an economic basis for schedule-protection investments, including buffer ore stockpiles, milestone-based contractor incentives, and conditional contingency reserves, with benefit-cost ratios ranging from 1.9 to 4.9. A five-year mining license extension was estimated to generate an additional $1,981 million in project value. Furthermore, monthly monitoring of development tonnage could identify potential schedule deviations as early as April 2027, rather than 2031, enabling earlier corrective interventions.
References
Alipour, A., Khodaiari, A. A., Jafari, A., & Tavakkoli-Moghaddam, R. (2022). An integrated approach to open-pit mines production scheduling. Resources Policy, 102459. https://doi.org/10.1016/j.resourpol.2021.102459
Auger, F., & Guzmán, J. I. (2010). How rational are investment decisions in the copper industry? Resources Policy, 35(4), 292–300.
Brealey, R. A., Myers, S. C., & Allen, F. (2020). Principles of corporate finance (13th ed.). McGraw-Hill Education.
Breay Myers Allen. (2003). Principles of Corporate Finace (p. 283).
Committee, F. O. M. (2025). Statement on longer-run goals and monetary policy strategy (amended effective August 22, 2025). Board of Governors of the Federal Reserve System. https://www.federalreserve.gov/monetarypolicy/monetary-policy-strategy-tools-and-communications-statement-on-longer-run-goals-monetary-policy-strategy-2025.htm
Del Castillo, M. F., & Dimitrakopoulos, R. (2019). Dynamically optimizing the strategic plan of mining complexes under supply uncertainty. Resources Policy, 60, 83–93. https://doi.org/10.1016/j.resourpol.2018.11.019
Espinoza, R. D., & Rojo, J. (2017). Towards sustainable mining (Part I): Valuing investment opportunities in the mining sector. In Resources Policy (Vol. 52, pp. 7–18). https://doi.org/10.1016/j.resourpol.2017.01.011
Flyvbjerg, B. (2014). What you should know about megaprojects and why: An overview. Project Management Journal, 45(2), 6–19.
Furtado e Faria, M., Dimitrakopoulos, R., & Lopes Pinto, C. L. (2022). Integrated stochastic optimization of stope design and long-term underground mine production scheduling. Resources Policy, 102918. https://doi.org/10.1016/j.resourpol.2022.102918
Haque, M. A., Topal, E., & Lilford, E. (2014). A numerical study for a mining project using real options valuation under commodity price uncertainty. Resources Policy, 39, 115–123. https://doi.org/10.1016/j.resourpol.2013.12.004
Jacobs, F. R., & Chase, R. B. (2018). Operations and supply chain management (15th ed.). McGraw-Hill Education.
Khan, A., & Asad, M. W. A. (2021). A mixed integer programming based cut-off grade model for open-pit mining of complex poly-metallic resources. Resources Policy, 102076. https://doi.org/10.1016/j.resourpol.2021.102076
LaRoche-Boisvert, M., Dimitrakopoulos, R., & Ferland, J. A. (2021). Simultaneous production scheduling and transportation optimization from mines to port under uncertain material supply. Resources Policy, 102150. https://doi.org/10.1016/j.resourpol.2021.102150
Lilford, E. (2023). Natural resources: Cost of capital and discounting – Risk and uncertainty. Resources Policy, 103242. https://doi.org/10.1016/j.resourpol.2022.103242
Lilford, E., Maybee, B., & Packey, D. (2018). Cost of capital and discount rates in cash flow valuations for resources projects. Resources Policy, 59, 525–531. https://doi.org/10.1016/j.resourpol.2018.09.008
Mangaonkar, Dr. M. (2024). Operations and Supply Chain Management. In Operations and Supply Chain Management. https://doi.org/10.59646/oscm/292
Merrow, E. W. (2011). Industrial megaprojects: Concepts, strategies, and practices for success. John Wiley & Sons.
Mudd, G. M., & Jowitt, S. M. (2018). Growing global copper resources, reserves and production: Discovery is not the only control on supply. In Economic Geology (Vol. 113, Number 6, pp. 1235–1267). https://doi.org/10.5382/econgeo.2018.4590
Nelis, G., Morales, N., & Jelvez, E. (2023). Optimal mining cut definition and short-term open pit production scheduling under geological uncertainty. Resources Policy, 103340. https://doi.org/10.1016/j.resourpol.2023.103340
Nesbitt, P., Blake, L. R., Lamas, P., Goycoolea, M., Pagnoncelli, B. K., Newman, A., & Brickey, A. (2021). Underground mine scheduling under uncertainty. European Journal of Operational Research, 294(1), 340–352.
Samis, M., Davis, G. A., Laughton, D., & Poulin, R. (2005). Valuing uncertain asset cash flows when there are no options: A real options approach. In Resources Policy (Vol. 30, Number 4, pp. 285–298). https://doi.org/10.1016/j.resourpol.2006.03.003
Savolainen, J. (2016). Real options in metal mining project valuation: Review of literature. In Resources Policy (Vol. 50, pp. 49–65). https://doi.org/10.1016/j.resourpol.2016.08.007
Shafiee, S., & Topal, E. (2010). An overview of global gold market and gold price forecasting. Resources Policy, 35(3), 178–189.
Sotoudeh, F., Nehring, M., Kizil, M., Knights, P., & Mousavi, A. (2020). Production scheduling optimisation for sublevel stoping mines using mathematical programming: A review of literature and future directions. Resources Policy, 101809. https://doi.org/10.1016/j.resourpol.2020.101809
Vallée, M. (2000). Mineral resource + engineering, economic and legal feasibility = ore reserve. CIM Bulletin, 93(1038), 53–61.
Yang, W., Fang, N., Wang, Y., Long, T., Deng, S., Xue, M., & Deng, B. (2022). Value evaluation of mining right based on fuzzy real options. Resources Policy, 102818. https://doi.org/10.1016/j.resourpol.2022.102818