Improving Construction Performances and Reducing Delay Through Lesson Learned and Project Management Office (PMO) Implementation: A Case Study of Kucing Liar Fan 7, PT. Freeport Indonesia

Authors

  • Rega Rinaldo Johnjudika Institut Teknologi Bandung
  • Gatot Yudoko Institut Teknologi Bandung

DOI:

https://doi.org/10.46799/adv.v4i9.652

Keywords:

Construction, Construction Performance, Project Delay, Lesson Learned, Project Management Office

Abstract

The Kucing Liar Fan 7 project is an underground ventilation construction project within the Central Services Division of PT Freeport Indonesia. The problems arose not from a single cause but from the interaction of management, construction method, material availability, people and communication, equipment, and the underground working environment. This study aims to identify and evaluate the key lessons learned from the Kucing Liar Fan 7 project, determine how these lessons can be institutionalized through a Project Management Office (PMO), and develop an implementation roadmap to improve future construction performance. A mixed-method approach was used, combining a five-point Likert questionnaire distributed to 27 project stakeholders across six factors (Management, Method, Material, People, Environment, Equipment) with historical project data, interviews, observation, and two sessions of Focus Group Discussion (FGD). The questionnaire results were analysed using mean scores, Relative Importance Index (RII), Cronbach's alpha, and Pareto analysis. The analysis identified Management, Method, Material, People, and Environment as the prioritized factors, jointly accounting for 84.93% of the cumulative relative importance, with root causes concentrated in design readiness, change control, material planning, communication, and constrained underground working space. The lessons learned were translated into a Lesson Learned Register and a phased Controlling PMO implementation roadmap consisting of organizational assessment, pilot implementation, organizational integration, and continuous improvement. The proposed PMO does not replace the existing balanced-matrix structure but strengthens governance, standardization, coordination, monitoring, and knowledge management to reduce the recurrence of delays in future underground ventilation construction projects.

References

Assaf, S. A., & Al-Hejji, S. (2006). Causes of delay in large construction projects. International Journal of Project Management, 24(4). https://doi.org/10.1016/j.ijproman.2005.11.010

Aubry, M., Hobbs, B., & Thuillier, D. (2007). A new framework for understanding organisational project management through the PMO. International Journal of Project Management, 25(4), 328–336. https://doi.org/10.1016/j.ijproman.2007.01.004

Aubry, M., Hobbs, B., & Thuillier, D. (2008). Organisational project management: An historical approach to the study of PMOs. International Journal of Project Management, 26(1), 38–43. https://doi.org/10.1016/j.ijproman.2007.08.009

Baruch, Y., & Holtom, B. C. (2008). Survey response rate levels and trends in organizational research. Human Relations, 61(8), 1139–1160.

Boone Jr., H. N., & Boone, D. A. (2012). Analyzing Likert data. Journal of Extension, 50(2).

Boonsripitayanon, W., & Jearasatit, V. (2017). Earned value management system for construction project performance evaluation. International Journal of Construction Engineering and Management, 6(4), 141–149.

Creswell, J. W., & Creswell, J. D. (2018). Research design: Qualitative, quantitative, and mixed methods approaches (5th ed., Ed.). Sage Publications.

Creswell, J. W., & Creswell, J. D. (2022). Research Design: Qualitative, Quantitative, and Mixed Methods Approaches (6, Ed.). SAGE Publications.

Cronbach, L. J. (1951). Coefficient alpha and the internal structure of tests. Psychometrika, 16(3), 297–334. https://doi.org/10.1007/BF02310555

Desouza, K. C., & Evaristo, J. R. (2006). Project management offices: A case of knowledge-based archetypes. International Journal of Information Management, 26(5), 414–423. https://doi.org/10.1016/j.ijinfomgt.2006.07.002

Doloi, H., Sawhney, A., Iyer, K. C., & Rentala, S. (2012). Analysing factors affecting delays in Indian construction projects. International Journal of Project Management, 30(4), 479–489. https://doi.org/10.1016/j.ijproman.2011.10.004

Eken, G., Bilgin, G., Dikmen, I., & Birgonul, M. T. (2020). A lessons learned tool for organizational learning in construction. Automation in Construction, 112, 103117.

Enshassi, A., Mohamed, S., & Abushaban, S. (2009). Factors affecting the performance of construction projects in the Gaza Strip. Journal of Civil Engineering and Management, 15(3), 269–280. https://doi.org/10.3846/1392-3730.2009.15.269-280

Hobbs, B., & Aubry, M. (2007). A multi-phase research program investigating project management offices (PMOs): The results of phase 1. Project Management Journal, 38(1), 74–86. https://doi.org/10.1177/875697280703800107

Hobbs, B., & Aubry, M. (2008). An empirically grounded search for a typology of project management offices. Project Management Journal, 39(S1), S69–S82. https://doi.org/10.1002/pmj.20072

Institute, P. M. (2017). Project management body of knowledge (PMBOK guide) (6th ed., Ed.). PMI.

Institute, P. M. (2019). Practice standard for earned value management (3rd ed.). Project Management Institute.

Jugdev, K. (2012). Learning from lessons learned: Project management research issues. Project Management Journal, 43(2), 6–10.

Kerzner, H. (2022). Project management: A systems approach to planning, scheduling, and controlling (13th ed.). Wiley.

Oakland, J. S. (2014). Total quality management and operational excellence: Text with cases (4th ed.). Routledge.

Sambasivan, M., & Soon, Y. W. (2007). Causes and effects of delays in Malaysian construction industry. International Journal of Project Management, 25(5), 517–526. https://doi.org/10.1016/j.ijproman.2006.11.007

Sweis, G., Sweis, R., Hammad, A. A., & Shboul, A. (2008). Delays in construction projects: The case of Jordan. International Journal of Project Management, 26(6), 665–674. https://doi.org/10.1016/j.ijproman.2007.09.009

Unger, B. N., Gemunden, H. G., & Aubry, M. (2012). The three roles of a project portfolio management office: Their impact on portfolio management execution and success. International Journal of Project Management, 30(5), 608–620. https://doi.org/10.1016/j.ijproman.2012.01.015

Downloads

Published

2026-09-23

How to Cite

Johnjudika, R. R., & Yudoko, G. . (2026). Improving Construction Performances and Reducing Delay Through Lesson Learned and Project Management Office (PMO) Implementation: A Case Study of Kucing Liar Fan 7, PT. Freeport Indonesia. Advances In Social Humanities Research, 4(9), 1078–1093. https://doi.org/10.46799/adv.v4i9.652